May 13, 1997
Dear Stakeholder:
Enclosed for your review and comment is a draft of the
regulations and preamble to revise the operating permits
regulations of part 70, and to revise the minor new source review
(NSR) requirements for part 51 relating to public participation.
Revisions to part 70 were proposed on August 29, 1994 and
August 31, 1995, and revisions to part 51 were proposed on
August 31, 1995. We are seeking your review because of the
length of time since the August 1995 proposal, and because
several of you have asked to see the package in detail. The
enclosed draft regulations and preamble reflect changes made as a
result of the many comments we received on the proposals.
There are several issues on which we would like you to focus
your comments. These include: (1) the provisions for minor
permit revisions; review by the Environmental Protection Agency
(EPA), affected States, and the public; and the eligibility
criteria for de minimis permit revisions; (2) the definition of
potential to emit, in response to the vacatur and remand of the
definition in Clean Air Implementation Project, et al. v. EPA
following petitioners' challenge to the definition's "Federal
enforceability" requirement; (3) the absence of a mandate for
emissions cap permits, including PAL's and advance NSR, as a
minimum element of State part 70 programs; and (4) EPA's
interpretation of the collocation procedures as applied to
unlisted sources of fugitive emissions.
In addition, we are including for your review and comment
three alternative approaches that are designed to address
concerns that have been raised about delays caused by potential
changes to the permit revision process. One approach provides
for post-hoc review procedures for minor permit revisions, and
two other approaches provide for expanding the criteria for de
minimis changes. These approaches have been developed as a
result of comments from members of the Permits, New Source
Review, and Toxics Subcommittee of the Clean Air Act Advisory
Committee. The three approaches are explained in a separate
enclosure, but the Agency has not developed regulatory or
preamble discussion for them. Concerns associated with each
approach are identified.
Please e-mail any comments or questions to the Clean Air Act Information
Network.
Return to the Clean Air
Act
Information Network Home Page
We also seek your comments on our approach to the emergency
defense provision. In August 1995, the Agency proposed to narrow
the affirmative defense for emergencies found at section 70.6(g),
limiting the defense to requirements established in the part 70
permit. In the draft final rule, the Agency has incorporated a
different approach, limiting the defense to technology-based
emission limits in State Implementation Plans. A question has
recently been raised as to whether part 70 is the appropriate
vehicle to provide for such a defense, or alternatively, whether
EPA should issue guidance on how such defenses may be
incorporated into SIPs. Thus, while the final draft contains a
proposal for an emergency defense in part 70, we solicit your
views on this issue as well.
As you know, we have scheduled a stakeholders' meeting for
May 28 in the Research Triangle Park, North Carolina (RTP, NC).
The meeting is scheduled from 9:00 a.m. to 4:30 p.m. Additional
logistics were faxed to each of you previously. At the meeting,
we intend to discuss the specific issues identified above. Our
goal following this meeting is to complete this rulemaking in a
timely manner.
We would like to receive your comments by June 12. Please
send them to Ray Vogel at MD-12, EPA, RTP, NC, 27711. I look
forward to receiving your comments and seeing you at the
stakeholders' meeting.
Sincerely,
/s/
Lydia N. Wegman
Deputy Director
Office of Air Quality Planning
and Standards
Enclosures
ENCLOSURE
OPTIONS FOR REDUCING DELAY
BACKGROUND
The draft rule requires public and EPA review prior to
issuance of permit revisions ("pre-hoc" review) for all changes
in the minor permit revision category (also called middle tier).
One of the options below allows "post-hoc" review by the public
and EPA. "Post-hoc" review means a process in which the permit
revision may be issued before the end of EPA and public review.
In a post-hoc review process, EPA and public review must begin at
least before the permit is revised. "Pre-hoc" review means that
all required opportunity for review (EPA, public, and affected
States) must be complete before the permit issues. In either
pre-hoc or post-hoc review, review by the permit authority occurs
prior to issuance of the permit revision.
The minor permit revision category includes: (1) nonmajor
netouts, (2) PTE limits that avoid major source requirements, and
(3) other minor NSR changes that are not eligible for the de
minimis category. (Nonmajor netouts mean changes that involve
netting where the emission increase from the project exceeds
PSD/NSR significance levels, but is less than major source
thresholds.)
In addition, the draft prohibits netting and PTE limits from
the de minimis category. Two options below would expand the de
minimis category to remove this prohibition and include certain
PTE limits and netouts. ("De minimis changes" mean a category of
changes that are exempt from public and EPA review and from
citizen petition. State programs allowing de minimis changes
must identify them in detail, demonstrate that they meet EPA
criteria, and gain EPA approval.)
The criteria for de minimis changes in the draft are that
any de minimis change must involve either minimal judgment, or
have /trivial environmental impact. The preamble discussion
gives examples of minimal judgment, and both the preamble and the
rule describe the showing States must make to demonstrate trivial
environmental impact. The draft allows States to presume that
any change that increases emissions less than 25 percent of
PSD/NSR significance levels has a trivial impact, and is
therefore de minimis. State programs using the presumptive 25
percent level are not required to demonstrate trivial
environmental impact; however, they must address any public
comments alleging that impacts at those levels are not trivial.
In addition, the draft rule allows States to reduce EPA's
review period to the public comment period (to be no less than 21
days) for minor permit revisions, if EPA and the public do not
comment adversely during the public comment period.OPTION 1
Option 1 would expand the de minimis category to include
certain PTE limits, and to include certain netting transactions
in serious or severe ozone nonattainment areas.
Option 1 would allow PTE limits to be de minimis, if the
limit involves minimal judgment AND the limit is less than 50
percent of the relevant major source or major modification
thresholds.
For this purpose, minimal judgment means limiting PTE
through limiting operating hours or production rates, and
estimating emissions by use of:
(1) materials balance;
(2) emission factors with A, B or C ratings; or
(3) stack-test data based on EPA test methods.
We do not include as representing minimal judgment the
following:
-- reliance on a calculated percent reduction from a
control device, capture ratio, transfer efficiency; or
-- case-by-case emission factors derived from sources
other than those listed above in (1), (2) or (3).
In addition, Option 1 would allow netting in serious/severe
nonattainment areas to be de minimis, if emissions from the
project are less than 25 percent of significance levels (e.g.,
6.25 tpy).
OPTION 2
Option 2 would allow post-hoc review for certain PTE limits
and netting transactions, as described below.
Option 2 would allow post-hoc review of PTE limits, unless
the both of the following criteria are met:
(1) the source relies on a substantially high degree of
reduction from control devices to achieve nonmajor
status, and
(2) the PTE limit is significantly close to relevant major
source/modification thresholds.
The State would select and define numbers in its program in
place of the imprecise terms "substantially high" degree of
reduction, and "significantly" close to relevant major
source/modification thresholds. The final rule would give
examples of changes that EPA believes are, and are not, eligible
under the above criteria. For example, a change that requires 90
percent reduction to meet its PTE limit, and the PTE limit is set
at 99 tpy for a 100 tpy threshold would meet the criteria and
require prior review. Conversely, a change that requires 80
percent reduction and the PTE limit is set at 80 tpy on a 100 tpy
threshold would be acceptable for post-hoc review.
In addition, Option 2 would allow post-hoc review of netouts
in serious/severe nonattainment areas, if emissions from the
project are less than 25 tpy and emissions from the 5-year
contemporaneous period are also less than 25 tpy.
There are numerous concerns with option 2. First, the Act
requires EPA review of title V permits prior to issuance, unless
the change is de minimis. Second, post-hoc review requires the
development of a new and complex process that is not provided for
expressly under Title V, and that is foreign to State permit
programs. Third, there are concerns about the liability issue.
Some hold that under post-hoc review, if it is found during post-hoc review that the issued permit is improper, sources should be
penalized only if found to be in noncompliance with the revised
permit. In effect, the post-hoc process would allow a permit
shield upon permit issuance, something EPA's part 70 rule has
never allowed prior to EPA and public review. Finally, the post-hoc process casts significant uncertainty on the State permit
until EPA and public review, and opportunity for public petition,
are completed.
OPTION 3
Instead of post-hoc review, Option 3 would expand the de
minimis category further to include more PTE limits and netouts
as described below. This option is an alternative to Option 2,
to be used if Option 2 is rejected, and there is a desire to
expand Option 1 beyond its current scope. The criteria for
option 3 are ill-defined currently, and comments from
stakeholders will be helpful in better defining the criteria.
Between now and the May 28 meeting EPA will develop option 3
further and present refinements on option 3 at the meeting.
Option 3 would add PTE limits to the de minimis category by
including more types of minimal judgment for PTE limits or by
raising the 50 percent ceiling under Option 1 to a somewhat
higher level.
In addition, Option 3 would add netouts to the de minimis
category by including netouts if the reductions necessary to net
relied on restricting PTE, and if the PTE restrictions met the
expanded de minimis criteria for PTE limits. Or, Option 3 would
raise the presumptive de minimis level to a higher percent of significance levels from its current 25 percent level in the
draft. This change would affect netouts only in serious/serious
area, though.
The concern with option 3, as with any de minimis category,
is the need to stay within the de minimis concept under Alabama
Power. Although the criteria in option 1 represent EPA's current
thinking on which PTE limits and netouts best meet the de minimis
concept under Alabama Power, the Agency is willing to explore
specific ways to include more changes in the de minimis category
that fit within the "minimal judgment" or the trivial
environmental impact criteria. Provided these alternatives are
in keeping with the de minimis concept under Alabama Power,
option 3 could be less risky, more legally justifiable, and
significantly less complex than Option 2.